Tuesday, July 15, 2008

July 15th


Progress is slow at the moment. Getting the anchor plates and hold downs ready for the special inspector, has been a problem. The framing crew seems to have fallen apart yesterday in a hail of accusations and anger. Four times the special inspector has been delayed because the crew either didn't have the holes drilled, then they didn't have the right drill bits and finally yesterday they discovered they didn't have the right bolts. We drove around trying to the get the materials they needed and meanwhile the inspector was cancelled yet again.

Obviously there is a problem in management and we think Ken, our framer, has taken his eye off the ball due to the discovery of his critically high blood pressure. Fortunately his numbers are now under control and perhaps he can get back to concentrating on our job.

Meanwhile we have placed our order to Bali and the work will take 7 to 8 weeks to complete and then 4 - 6 weeks on the water. We won't have it until about Nov. 1st. I called the stucco people to ask if this would be a problem. While it isn't ideal, they can work around it.

No comments:

Post a Comment